During the current phase the project will
implement the following activities:
|
- Until December, 2001
Creating the Project Team
Designing action plan
Defining working methodology
Starting awareness campaign
Recruiting staff for field work
Developing working materials and tools including questionnaires
|
- January, 2002
Preparing the survey
Identifying focal points
Training the teams for field work
Making appointments with stakeholders
|
- February, 2002
Meeting key people within envisaged institutions
Training the teams for field work
Starting survey in Maputo City only (for piloting purposes)
|
- March, 2002
Evaluating preliminary results from Maputo survey
Developing National SCAN ICT web page (draft)
|
- April - May, 2002
Finalizing the survey in Maputo
Analyzing and evaluating the collected data
|
- June - August, 2002
Extending survey to the rest of the country
Evaluating preliminary results from the other provinces
Finalizing the survey
|
- September - October, 2002
Analyzing and evaluating the collected data
Preparing and delivering final report
Delivering the Document on Methodology
Delivering National SCAN ICT web page
|
| |
| |
| |